- Sunday, August 19
- Friday, August 17
- Thursday, August 16
- Wednesday, August 15
- Monday, August 13
- Saturday, August 11
- Friday, August 10
- Wednesday, August 08
- Monday, August 06
- Saturday, August 04
- Thursday, August 02
- Wednesday, August 01
- Tuesday, July 31
- Monday, July 30
- Sunday, July 29
- Saturday, July 28
- Friday, July 27
- Thursday, July 26
- Monday, July 23
- Friday, July 20
- Thursday, July 19
- Tuesday, July 17
- Monday, July 16
- Saturday, July 14
- Friday, July 13
- Thursday, July 12
- Wednesday, July 11
- Saturday, July 30
- Friday, July 29
- Sunday, July 24
- Saturday, July 23
- Friday, July 22
- Thursday, July 21
- Wednesday, July 20
- Monday, July 18
- Sunday, July 17
- Saturday, July 16
- Friday, July 15
- Thursday, July 14
- Wednesday, July 13
- Tuesday, July 12
- Monday, July 11
- Sunday, July 10
- Sunday, July 10
- Saturday, July 09
- Thursday, July 07
- Tuesday, July 05
- Sunday, July 03
- Friday, July 01
- Thursday, June 30
- Wednesday, June 29
- Tuesday, June 28
- Monday, June 27
- Friday, June 03
- Wednesday, June 01
August 2012
July 2012
April 2012
March 2012
January 2012
October 2011
September 2011
August 2011
July 2011
June 2011
March 2011
February 2011
October 2010
June 2010
May 2010
April 2010
Update on Cable Installation
Wednesday, August 10, 2011
We are making good progress, and the weather has been beautiful today.
We have completed plow burial on Segment 2 and Segment 3 over the past couple days, and we are now switching back to ROV operations to bury the ends of these two segments to protect them from fishing activity. ROV work is a bit tedious, and it will be a few more days before we start again with plow installation of our last segment (Segment 4). We are looking forward to this event!
--Cecile Durand, OOI Regional Scale Nodes Marine Maintenance Manager at the University of Washington, reports from aboard the TE SubCom Dependable.