- Sunday, August 19
- Friday, August 17
- Thursday, August 16
- Wednesday, August 15
- Monday, August 13
- Saturday, August 11
- Friday, August 10
- Wednesday, August 08
- Monday, August 06
- Saturday, August 04
- Thursday, August 02
- Wednesday, August 01
- Tuesday, July 31
- Monday, July 30
- Sunday, July 29
- Saturday, July 28
- Friday, July 27
- Thursday, July 26
- Monday, July 23
- Friday, July 20
- Thursday, July 19
- Tuesday, July 17
- Monday, July 16
- Saturday, July 14
- Friday, July 13
- Thursday, July 12
- Wednesday, July 11
- Saturday, July 30
- Friday, July 29
- Sunday, July 24
- Saturday, July 23
- Friday, July 22
- Thursday, July 21
- Wednesday, July 20
- Monday, July 18
- Sunday, July 17
- Saturday, July 16
- Friday, July 15
- Thursday, July 14
- Wednesday, July 13
- Tuesday, July 12
- Monday, July 11
- Sunday, July 10
- Sunday, July 10
- Saturday, July 09
- Thursday, July 07
- Tuesday, July 05
- Sunday, July 03
- Friday, July 01
- Thursday, June 30
- Wednesday, June 29
- Tuesday, June 28
- Monday, June 27
- Friday, June 03
- Wednesday, June 01
August 2012
July 2012
April 2012
March 2012
January 2012
October 2011
September 2011
August 2011
July 2011
June 2011
March 2011
February 2011
October 2010
June 2010
May 2010
April 2010
Slideshow
Cable Deployment Update
Tuesday, July 05, 2011
Loading the player...
235 Km of the OOI cable have been deployed; 625 km remains to be deployed. Video shows the OOI cable running through the linear cable engine.
The TE SubCom Dependable is currently sailing through moderate to heavy seas at sea state 5 with 25 knots of wind from the North and waves topping 2.5 Meters in Height.
Despite the wind and seas, cable operations are currently in progress at a ship’s speed of .5 knots.