Blog
Node Installations Complete!
Sunday, August 19, 2012
Primary Node 3B has been deployed and OOI RSN primary node installation operations are complete. ...
Six on the Seafloor
Friday, August 17, 2012
Another major milestone for the OOI RSN has been achieved with the successful deployment of Primary Node 3A. ...
Shore Station Activities
Thursday, August 16, 2012
Much of the action during the OOI RSN primary node installation work has been taking place at sea on the TE SubCom Dependable. ...
New Seg. 7 Installation
Wednesday, August 15, 2012
Steady progress continues to be made on the installation of the northern section of the OOI cabled infrastructure to Axial Seamount. ...
Defining the SIA
Monday, August 13, 2012
The SIA is the Science Interface Assembly, which has all the active optics, communications, low-voltage power, and control circuitry in the primary nodes. ...
PN5A Successfully Deployed ...
Saturday, August 11, 2012
The OOI RSN program has achieved another major milestone! The Mid-Plate Node, Primary Node 5A, was deployed. ...
PN 5A – Jointing Operation ...
Friday, August 10, 2012
Steady progress continues to be made on the installation of Primary Node 5A. Buoy operations have been completed. ...
PN 5A Installation Continu ...
Wednesday, August 08, 2012
As we continue to work about 245 km off the coast of Oregon, we are making steady progress on the installation of OOI RSN Primary Node 5A. ...
On Site to Install PN5A
Monday, August 06, 2012
Brian Ittig, the OOI RSN Marine Operations Manager at the University of Washington, reports from the TE SubCom Dependable ...
Transit to Node 5A
Saturday, August 04, 2012
According to Paul Hagstrom, the ship left the dock in Portland, Oregon, at 1300h PDT on Friday, August 3, and was crossing the Columbia River Bar at Astoria some 8 hours later. ...
Port Call in Portland
Thursday, August 02, 2012
We arrived offshore of Astoria, Oregon, in the early morning hours today on our way back to Portland for a quick turnaround. ...
PN1D is Installed!
Wednesday, August 01, 2012
OOI Primary Node 1D has been deployed and landed on the seafloor and has been successfully tested from the shore station. ...
Burial and Inspection Comp ...
Tuesday, July 31, 2012
Burial and inspection of cable segments 3 and 4 were completed on 30 July 2012. Next up is installation of OOI Primary Node 1D. ...
Humpbacks Visit
Monday, July 30, 2012
As part of the OOI team at sea for the primary node installation cruise, the job of the two Protected Species Visual Observers (PSVO ...
Cable Burial Node PN1C
Sunday, July 29, 2012
Burial continues for cable segments 3 and 4, which are jointed into OOI RSN Primary Node 1C (PN1C). Photos here show deployment of PN1C. ...
Milestone: PN1C is Install ...
Saturday, July 28, 2012
On Friday, July 27, during cable balancing 433 meters of cable were removed from Segment 3 and 369 meters from Segment 4. ...
Photos of Final Inspection ...
Friday, July 27, 2012
Photos have just arrived from the TE SubCom Dependable of the final inspection of OOI RSN Primary Node 1B (PN1B). ...
Another RSN Node is Born! ...
Thursday, July 26, 2012
On July 26th at 4 pm PDT, the third Primary Node on the RSN (PN1C) came to life as power was re-applied to the cable system and energized the Node ...
Cable Burial Continues at ...
Monday, July 23, 2012
Burial of cable Segments 2 and 3, which are connected to Primary Node 1B, is continuing. ...
Second Node Installed!
Friday, July 20, 2012
Operations for the deployment of Primary Node 1B (PN1B) started late in the evening of July 19. Just before midnight it was confirmed that the node had landed. ...
Splicing Node PN1B into Se ...
Thursday, July 19, 2012
Splicing of Primary Node PN1B into segment 3 was completed over night and finished by 9:00am this morning. ...
Recovering End of Segment ...
Tuesday, July 17, 2012
By 0300h the end of cable Segment 2 was buoyed off and we were headed to the end of our next cable segment (3), a few miles away. ...
Word for the Day: Persiste ...
Monday, July 16, 2012
After 2 days of continuous effort, 3 grapnel runs, and 3 remotely operated vehicle (ROV) dive attempts, we finally recovered the shallow end of c ...
Major Milestone: First Nod ...
Saturday, July 14, 2012
By 4 pm today, Primary Node 1A had been successfully landed on the seafloor to within an incredibly-precise 35 meters of the intended position ...